Erosion and Sedimentation Control

LEED® Point Affected:

Objectives:

Activities Included:

Documentation

Schedule E1 - Using a checklist, conduct an inspection of all erosion and sedimentation control measures implemented onsite each week and following any significant storm event.  Photographic evidence must be submitted each week of each measure taken.  Inspections shall commence when the site work begins and will continue until final landscaping is complete.

Schedule E2 - Complete a log on a weekly basis and must document deficiencies related to the measures described in E1 and any corrective actions taken to remedy the deficiencies.

Download Erosion and Sedimentation Control PDF.

Download Erosion and Sedimentation Control ESC-06 Detail Inlet PDF.

Download Erosion and Sedimentation Control ESC-04 Detail Silt PDF.

Download Erosion and Sedimentation Contro lESC-01 Detail Stabi PDF.